School Bond Projects

2024 Mill & Bond - Investing in Excellence

Thanks to the support of our community, the Cherry Creek School District can continue to deliver excellence for our students, staff, and community.

The overwhelming support for the 2024 Mill and Bond helps to ensure high-quality teachers, innovation and in-demand career training, and safe, healthy schools for all students. The 2024 Bond is funding capital construction improvements across the district, with many of the projects underway.

The Cherry Creek PreK-12 Campus bond project is a multi-year process to replace aging and deteriorating buildings on the Cherry Creek PreK-12 Campus, starting with Cherry Creek High School in Phase I. The campus, encompassing Cherry Creek HS, Campus MS, and Belleview ES, is home to some of the oldest buildings in the district, including the West Building on the campus of Cherry Creek HS which was built in 1955. In recent years, buildings on the campus have been challenged with aging infrastructure, specifically the West Building, which will be the primary focus of Phase I.

Phase I

Phase I will begin with the demolition of the two district administrative office buildings on the site in order to make room for the new West Building. The existing West Building will be replaced with two new buildings—one dedicated to academics and the other to athletics. Phase I will also include redeveloped parking areas and a primary vehicular entry to campus from Union Avenue. The current parking lot west of the Stutler Bowl will become a parking lot for the high school.

Phase II

Phase II of the project will be included in a possible 2028 bond package and will add two new buildings dedicated to academics and the arts, a new pool as part of the West Building, and an expansion of the Phase 1 athletic building. It will also include additional parking.

If a 2028 bond is unsuccessful, the rest of CCHS will not be rebuilt; however all buildings included in Phase I will be fully completed.

UPDATE (May 2026): A master plan to envision how to rebuild the entire CCHS PK-12 campus was presented to district and school leadership nearly two years ago. The original master plan indicated that the West Building could be completed in one building. Once the actual design process began, it was determined one building would not be sufficient to replace all the academic spaces in the West Building. That triggered the need for a second building and therefore the need to move the tennis courts.  The decision was made to keep the current pool in order to prioritize academic learning spaces and maximize the taxpayer investment in the current pool since it was recently renovated as part of the 2012 bond.

Presentation of Phase I and Phase II plans 
given at the May 4, 2026 Community Meeting

Video showing future look of CCHS campus

Rebuild Renderings

CCHS End of Phase 1 Birds Eye Image looking SW - 20260506
CCHS End of Phase 1 Birds Eye Image looking NE - 20260506
CCHS End of Phase 1 Birds Eye Image looking NW - 20260506
External view of new academics building
New breakout area
external view of athletics building
External view of space between new buildings
view of new gym
view of new lobby outside of gym

Estimated Cost:
$220 million

Construction Schedule:

  • Late February 2026: CCSD staff to vacate ESC and OFS buildings
  • March 2-13, 2026: ESC & OFS Abatement - buildings will be closed and inaccessible
  • March 16-20, 2026 (CCSD Spring Break): ESC & OFS Police and Fire Training to allow for local jurisdictions to access the buildings and conduct trainings
  • March 16-20, 2026 (CCSD Spring Break): ESC & OFS Demolition Preparation in partnership with local police and fire departments
  • March 16-August 16, 2026: Tennis Court Relocation / Construction at Belleview Fields
  • March 30-April 24, 2026: ESC & OFS Demolition
  • Fall 2026: Opening of the new tennis courts and turf field in Belleview Park
  • Summer 2028: Estimated completion of construction and occupancy of new West Buildings
  • Fall 2028: Demolition of the existing West Building; Construction of the new north parking lot and designated drop off area

Community Engagement:

  • Spring 2024: Master planning process with 7 stakeholder/community meetings
  • Summer/Fall 2024: Multiple meetings with the City of Greenwood Village leadership
  • July 2024: Presentation to Greenwood Village City Council
  • September 2024: Feeder Bond Presentation
  • Spring/Summer: Multiple meetings with the City of Greenwood Village leadership
  • September 2025: CCHS Parent Group Meetings
  • November 2025: Community Meeting
  • May 2026: Community Meeting - view presentation from meeting